DDA
Home   |   Photo Gallery   |   Suggestions   |   Newsletter   |   Sitemap   |   Contact us
Navigation Navigation Navigation
Navigation Navigation Navigation
Navigation Navigation Navigation
»  Launch of TOD Workshop Series
»  Project 24- Approved proposal of Traffic & Circulation Plan around the Multi-level Car Parking at Kamla Nagar
»  New Project 31 for Approval - Proposal for Widening and upgradation of Mandi Road(MG Road to Delhi Haryana Border)in NCT of Delhi.
»  Project 17- Comprehensive Proposal on Vikas Marg Metro connectivity & Parking Strategies.
»  Project 21-Intersection Design & Widening proposal for Poorvi Marg - Outer Ring Road intersection.
»  Project 22- Improvement of ‘T’ Junction at Samalkha Chowk
»  Project 23- Traffic Circulation and Management Plan for S.P. Mukherjee Marg.
»  MINUTES OF THE 38TH MEETING OF UTTIPEC GOVERNING BODY HELD ON 26.07.2012
»  Traffic Circulation Plan Kushak Nallah depot GNCTD
»  Street Design Guidelines
»  Street Design Checklist
»  FOB Consideration and Design Checklist
»  List of Empanelled Consultants, UTTIPEC.
»  Format for Proposal Submission
»  Guideline for Road Marking
»  Pedestrian Design Guidelines
»  Transit Oriented Development (TOD)
Navigation Navigation Navigation
Navigation Navigation Navigation
»  Focus on public transport Govt. Body issue guidelines for seamless travel.
»  New Articles from AAUI Dated 24.01.2011
»  Lecture Organized by UTTIPEC at IIC dated 13.01.2011
»  PRESENTAION MADE ON 13.01.2011 AT IIC DURING THE LECTURE ORGANIZED BY UTTIPEC
»  Crackdown on illegal parking
»  Grand plan: Integrate all transport in Delhi, NCR
»  Gazette Notification dated 07.08.2009
Navigation Navigation Navigation


Project 15-Construction of RUB at level crossing adjacent to Roshnara Garden

1

Name of the Project

Construction of RUB at level crossing adjacent to Roshnara Garden

2

Name of the Agency

Municipal Corporation of Delhi

3

Consultants:   

M/s Park Projects Consultants  Pvt.Ltd  New Delhi

4

UTTIPEC Processing

RUB at Railway level crossing Roshnara Bagh (MCD) was presented in working Group-II B  meeting dated 13.11.09 with the following observations and decisions:

Decision of Working Group

      i.   There is acute constraint of space between proposed under-pass and the 'T' intersection, which does not allow a full proof solution for the traffic particularly the pedestrian/non-motorized traffic and the right turning movements on the intersection. The proposed solution is a compromise under the pressing circumstances when project authorities have decided to go ahead with the proposal.

 

     ii.    The consultant was requested to work out in detail, the alternative proposal by considering 30mt. road at  both  'U' loop  locations with the recommendations at (v) of observations part.

 

    iii.     Project Manager agreed to modify the proposal on the above lines and submit the appropriate drawings to UTTIPEC so that the same can be placed before the next Governing Body Meeting for its consideration.

 

Decision of Governing Body

The Governing Body in its meeting dated 23.12.2009 approved the scheme with the observations of WG-II-B and desired that before releasing the scheme, it may be seen by EM, DDA/Chairman WG-II-B.

5

 Copy of the approved plan:

6

For additional details

Executive Engineer
(Pr.) CLZ, MCD,
Sindhora Kalan,
Shakti Nagar,
Delhi -110007.

Back