»  Launch of TOD Workshop Series
»  Project 24- Approved proposal of Traffic & Circulation Plan around the Multi-level Car Parking at Kamla Nagar
»  New Project 31 for Approval - Proposal for Widening and upgradation of Mandi Road(MG Road to Delhi Haryana Border)in NCT of Delhi.
»  Project 17- Comprehensive Proposal on Vikas Marg Metro connectivity & Parking Strategies.
»  Project 21-Intersection Design & Widening proposal for Poorvi Marg - Outer Ring Road intersection.
»  Project 22- Improvement of ‘T’ Junction at Samalkha Chowk
»  Project 23- Traffic Circulation and Management Plan for S.P. Mukherjee Marg.
»  MINUTES OF THE 38TH MEETING OF UTTIPEC GOVERNING BODY HELD ON 26.07.2012
»  Traffic Circulation Plan Kushak Nallah depot GNCTD
»  Street Design Guidelines
»  Street Design Checklist
»  FOB Consideration and Design Checklist
»  List of Empanelled Consultants, UTTIPEC.
»  Format for Proposal Submission
»  Guideline for Road Marking
»  Pedestrian Design Guidelines
»  Transit Oriented Development (TOD)
Navigation Navigation Navigation
Navigation Navigation Navigation
»  Focus on public transport Govt. Body issue guidelines for seamless travel.
»  New Articles from AAUI Dated 24.01.2011
»  Lecture Organized by UTTIPEC at IIC dated 13.01.2011
»  PRESENTAION MADE ON 13.01.2011 AT IIC DURING THE LECTURE ORGANIZED BY UTTIPEC
»  Crackdown on illegal parking
»  Grand plan: Integrate all transport in Delhi, NCR
»  Gazette Notification dated 07.08.2009
Navigation Navigation Navigation


Project 12-Proposal for comprehensive development of corridor (Outer Ring Road) between Vikas Puri to Meera Bagh

1

Name of the Project

Proposal for comprehensive development of corridor (Outer Ring Road) between Vikas Puri to Meera Bagh

2

Name of the Agency

PWD, Govt of NCT,Delhi

3.

Consultants:

L&Q Survys Pvt. Ltd.,

1/103, Manas  Apartment,
Mayur Vihar, Phase – I

New Delhi-91
Ph. 23586782, 9811039706

4.

Project Scheduled

a.     Likely to be started by December, 2010.

b.    Likely to be completed by June, 2013.

5

UTTIPEC Processing

a.    The project of PWD was considered by UTTIPEC Working Group IIB in its meeting dt.16.03.09. and the proposal was recommended for consideration & approval by the UTTIPEC Governing Body with the following decisions / observations :-

 

     I.        As far as possible the continuity of interference–free footpaths and cycle tracks at intersections be shown.

    II.        Traffic management plan/circulation plan for an area of around 1 km. along the both sides of ORR be prepared. Free left turn may be avoided at the intersections, even in case of signalized crossing.

  III.        Slip roads and service roads wherever feasible, may be provided

   IV.        Width of service road, including footpath, may be at least 7.5 meters.

    V.        Provisions for segregated lanes and facilities for public transport system, including bus shops, be ensured.

   VI.        Traffic signals be shown at all intersections with provision for separate signal phase for cars, buses, NMT. Signal timings be calculated as per the traffic projections.

 VII.        Location of signage be shown in the plans.

VIII.        The details of affected structures and trees /bushes be given in the feasibility format.

   IX.        Right of Way line of all roads as per the Master Plan / Zonal Development Plan be shown   in the plan. Proposed Right of way (ROW) of Ring Road to be shown as 63.5mt.(200 ft.) in   bold chain line.

    X.        A traffic management plan and a work zone Management plan during the construction period be prepared.

   XI.        Feasibility report should clearly indicate the location, area, type of affected structures and disputed land/land under stay etc.  on the plan and also in the form of a report which is  to be presented before the Governing Body meeting on 20.3.2009.

 

b.    UTTIPEC Governing body in its meeting held on 20.3.09 under the chairmanship of Hon'ble L.G, Delhi  accorded its  approval, based on the recommendation and observation/concern of the working group meeting  with following additional observations:-

 

     I.        Project must consider clear 11 mtr. elevated road,  instead of 9 mtr in the entire stretch from Wazirabad to Vikas puri (Also covered 3 projects earlier approved by the last Governing Body on 20.2.09).

    II.        The needs of pedestrians, bus passengers & cyclists be also ensured in micro details, based on the input from UTTIPEC core team.

  III.        To meet the requirement of proper merging & de-merging, lengths; additional land reservations be made (more than the proposed right of way) at key intersections in the LOP/ZDP/MP.

   IV.        PWD, GNCT Delhi to submit an integrated proposal of entire outer ring road corridor from Wazirabad up to Meera Bagh./Vikas Puri (also covered  3 projects earlier approved by the last Governing Body on 20.2.2009).

    V.        The traffic management/work zone management plan during construction be prepared in consultation with Traffic Police, for the influence area of about 1 k.m. on either side of the road. 

   VI.        Immediately on receipt of the integrated proposal of Wazirabad to Vikaspuri corridor from PWD, GNCTD with above details, the same be uploaded on UTTIPEC web site for information of all concerned.

 

6

Location Map : 

 

7.

Copy of the approved plan:

DESIGN_PLAN_final on 17 feb Layout1 (1)

 DESIGN_PLAN_final on 17 feb Layout1 (2)

 DESIGN_PLAN_final on 17 feb Layout1 (3)

 DESIGN_PLAN_final on 17 feb Layout1 (4)

 DESIGN_PLAN_final on 17 feb Layout1 (5)

6

For additional details

kindly contact  Project Manager
(Flyover project- circle F-13), PWD,
Mukarba Chowk, Delhi

Ph: 27691871, Mob: 9818180952.

 