»  Launch of TOD Workshop Series
»  Project 24- Approved proposal of Traffic & Circulation Plan around the Multi-level Car Parking at Kamla Nagar
»  New Project 31 for Approval - Proposal for Widening and upgradation of Mandi Road(MG Road to Delhi Haryana Border)in NCT of Delhi.
»  Project 17- Comprehensive Proposal on Vikas Marg Metro connectivity & Parking Strategies.
»  Project 21-Intersection Design & Widening proposal for Poorvi Marg - Outer Ring Road intersection.
»  Project 22- Improvement of ‘T’ Junction at Samalkha Chowk
»  Project 23- Traffic Circulation and Management Plan for S.P. Mukherjee Marg.
»  MINUTES OF THE 38TH MEETING OF UTTIPEC GOVERNING BODY HELD ON 26.07.2012
»  Traffic Circulation Plan Kushak Nallah depot GNCTD
»  Street Design Guidelines
»  Street Design Checklist
»  FOB Consideration and Design Checklist
»  List of Empanelled Consultants, UTTIPEC.
»  Format for Proposal Submission
»  Guideline for Road Marking
»  Pedestrian Design Guidelines
»  Transit Oriented Development (TOD)
Navigation Navigation Navigation
Navigation Navigation Navigation
»  Focus on public transport Govt. Body issue guidelines for seamless travel.
»  New Articles from AAUI Dated 24.01.2011
»  Lecture Organized by UTTIPEC at IIC dated 13.01.2011
»  PRESENTAION MADE ON 13.01.2011 AT IIC DURING THE LECTURE ORGANIZED BY UTTIPEC
»  Crackdown on illegal parking
»  Grand plan: Integrate all transport in Delhi, NCR
»  Gazette Notification dated 07.08.2009
Navigation Navigation Navigation


Project 5- Proposal for comprehensive development of corridor (Outer Ring Road) between Mangolpuri to Madhuban Chowk

1

Name of the Project

Proposal for comprehensive development of corridor (Outer Ring Road) between Mangolpuri to Madhuban Chowk

2

Name of the Agency

P.W.D, Govt. of NCT, Delhi.

3

Consultants

Consulting Engineers Group Ltd.,
207-208, DDA, Local Shopping Complex
Vikaspuri, New Delhi-110018
Ph. Office - 011-28542899, 9313752011

4

Project Scheduled

a)     Likely to be started by December,  2010.

b)     Likely to be completed by June, 2013.

 

5

UTTIPEC Processing

The project of PWD was considered by UTTIPEC Working Group II-B in its meeting dt.19.02.09 and the proposal was recommended for consideration & approval by the UTTIPEC Governing Body with the following decisions/observations :- 

      i.        Entry to/Exit from Rohini Sector-3, District Center be suitably modified by integrating approved layout plan of the District Centre and PSP Complex of Rohini Sector-3.  A dedicated service road may be provided for entry/exit to the parking and the buildings in complexes.          

     ii.        The existing flyover on Mangol Puri Chowk be extended and merged with proposed Som Vihar elevated road.

    iii.        The proposed Underpass on Deepali Chowk may be re-examined, and whether it could be deleted.              

   iv.        The Madhuban Chowk intersection be improved, to make it congestion free.

Observations/suggestions:                                    

 

      i.        As far as possible the continuity of interference–free footpaths and cycle tracks at intersections be shown.

 

     ii.        Traffic management plan/circulation plan for an area of around 1 km. along the both sides of ORR be prepared. Free left turn may be avoided at the intersections, even in case of signalized crossing.

 

    iii.        Slip roads and service roads wherever feasible, may be provided.

 

   iv.        Width of service road, including footpath, may be at least 7.5 meters.

 

    v.        Provisions for segregated lanes and facilities for public transport system, including bus shops, be ensured.

 

   vi.        Traffic signals be shown at all intersections with provision for separate signal phase for cars, buses, NMT. Signal timings be calculated as per the traffic projections.    

 

  vii.        Location of signage be shown in the plans.

 

 viii.        The details of effected structures and trees/bushes be given in the feasibility format.

 

   ix.        Right of Way line of all roads as per the Master Plan/Zonal Development Plan be shown in the plan.

 

    x.        A traffic management plan and a work zone management plan during the construction period be prepared.

 

   xi.        Width of the flyover/elevated road on outer ring road to be maintained as per the existing under pass on Madhuban Chowk.

 

UTTIPEC Governing Body in its meeting held on 20.2.09 under the Chairmanship of Hon'ble L.G, Delhi accorded its approval, based on the recommendation and observation/concern of the Working Group meeting  with following additional observations:-

 

      i.        Conflict free local movements, for all categories of traffic including pedestrians/cyclists at the junctions, as per advice of traffic police, MCD, and UTTIPEC experts be incorporated in the proposal.

     ii.        Traffic Management/work zone management plan during construction be prepared in consultation with traffic police for the influence area of about 1 km on either side of the road.

6

Location Map

 

7

Copy of the approved plan

Layout Plan 1, Layout Plan 2, Layout Plan 3, Layout Plan 4.

8

Issue under process

 

9

For additional details

Kindly Contact: - Project Manager
(Flyover project- circle F-13),
P.W.D, Mukarba Chowk, Delhi.      
Ph: 011-27691871, Mob: 9818180952.