DDA
Home   |   Photo Gallery   |   Suggestions   |   Newsletter   |   Sitemap   |   Contact us
Navigation Navigation Navigation
Navigation Navigation Navigation
Navigation Navigation Navigation
»  Advertisement for Consultant Job Positions in UTTIPEC (March 2015)
»  Launch of TOD Workshop Series
»  Expression of Interest” from interested Pvt./Public firms/ NGO’s both national and international,
»  Street Design Guidelines
»  Street Design Checklist
»  FOB Consideration and Design Checklist
»  List of Empanelled Consultants / Firms / Agencies of UTTIPEC.
»  UTTIPEC Standard Format / TORs
»  Guideline for Road Marking
»  Pedestrian Design Guidelines
Navigation Navigation Navigation
Navigation Navigation Navigation
»  Focus on public transport Govt. Body issue guidelines for seamless travel.
»  New Articles from AAUI Dated 24.01.2011
»  Lecture Organized by UTTIPEC at IIC dated 13.01.2011
»  PRESENTAION MADE ON 13.01.2011 AT IIC DURING THE LECTURE ORGANIZED BY UTTIPEC
»  Crackdown on illegal parking
»  Grand plan: Integrate all transport in Delhi, NCR
»  Gazette Notification dated 07.08.2009
Navigation Navigation Navigation


Project-47: Extension of Ashram Flyover to DND/Ring Road

1.        

Name of Project

Extension of Ashram Flyover to DND/Ring Road

2.        

Name of the Agency

PWD

3.        

Consultant

Feedback Infra Pvt. Ltd.

4.        

Copy of Proposal /Presentation

Conceptual traffic circulation plan

5.        

UTTPEC Processing

The project was discussed in UTTIPEC Working Group-II-B meeting under the Chairmanship of Secretary, PWD on 08.03.2017.  The background, project, details, observations, recommendations of Working Group-II-B meeting are as follows:

 

Background & Proposal

a)      Earlier, following two proposed options submitted and presented by PWD, GNCTD in 47th UTTIPEC WG-II-B meeting dated 26.5.2014 for providing right turn for vehicles on Ring Road for the residents of Kilokri Village towards Lajpat Nagar side. These are as follows:

     Option-I

Extension of Ashram flyover over Maharani Bagh intersection and its landing in front of Kilokri village for providing right turn for the people of Kilokri towards Lajpat Nagar side.

     Option-II

Provision of 'U'-turn at DND intersection for traffic coming from Kilokri Village towards Lajpat Nagar side.

      Earlier, Working Group dated 26.5.2014 recommended option-2 i.e. 'Provision of 'U' Turn at DND Intersection on Ring Road' for consideration of the Governing Body.  Accordingly, Governing Body in its meeting dated 25.6.2014 approved option 2 i.e. 'Provision of 'U' turn at DND Intersection on Ring Road'.

b)     Subsequently, PWD vide letter dated 21.2.2017 re-submitted the proposal of extension of Ashram Flyover upto DND flyover (earlier submitted option-1) and the same was presented by Chief Project Manager F- 2&3, PWD, GNCTD in this WG-II-B meeting dated 8.3.17 .

 

Observation

    PWD to integrate Kalindi bypass interchange in the  proposal.

Recommendation

        Working Group recommended the proposal for uploading on UTTIPEC website for community feedback and accordingly for consideration of the Governing Body.

 

Decision of The Governing Body dated 22.06.2017:

The Governing Body approved the proposal of Extension of Ashram Flyover to DND/Ring Road.

6.        

Date of Uploading the project

 15.11.2017

 

7.        

Additional Details

Executive Engineer

Flyover Project, ITPO Project Division,

PWD, GNCTD

Bhairon Marg T-Junction,

Near Pragati Power Station,

Ring Road

New Delhi-110002, Tel: 011-23378558